Lagoon Upgrades Phase 2

Georgetown, Prince Edward Island

completeWastewaterMRIF
Federal contribution
$142,911
Federal share24%

of $598.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
2007200920112013
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Georgetown
Construction start
Mar 1, 2010(actual)
Construction end
Dec 31, 2012(actual)

Against the original forecast

  • Construction start3.5 years lateforecast Sep 1, 2006
  • Construction end9 months lateforecast Mar 30, 2012

Also in Georgetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15645 in the federal list. How to read these figures.