Georgetown Water System - Modifications and Extensions of Watermains

Georgetown, Prince Edward Island

completeDrinking WaterMRIF
Federal contribution
$123,310
Federal share31%

of $393.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
200720082009
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Aug 19, 2007(actual)
Construction end
Feb 19, 2009(actual)

Against the original forecast

  • Construction start9 months lateforecast Nov 3, 2006
  • Construction end7 weeks lateforecast Dec 31, 2008

Also in Georgetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15688 in the federal list. How to read these figures.