Georgetown Water System - Safety Upgrades

Georgetown, Prince Edward Island

completeDrinking WaterMRIF
Federal contribution
$74,667
Federal share33%

of $224.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
200720082009201020112012
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Nov 1, 2007(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction start15 months lateforecast Aug 3, 2006
  • Construction end3 years lateforecast Nov 30, 2008

Also in Georgetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15669 in the federal list. How to read these figures.