Georgetown Water System Building Upgrades and Monitoring System Installation
Georgetown, Prince Edward Island
Federal contribution
$14,940
Federal share33%
of $44.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
2007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Environmental Industrial Services Inc.
- Construction start
- Apr 15, 2007(actual)
- Construction end
- Jul 1, 2007(actual)
Against the original forecast
- Construction start8 months lateforecast Jul 31, 2006
- Construction end7 months lateforecast Nov 30, 2006