Georgetown Water System Building Upgrades and Monitoring System Installation

Georgetown, Prince Edward Island

completeDrinking WaterMRIF
Federal contribution
$14,940
Federal share33%

of $44.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
2007
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Apr 15, 2007(actual)
Construction end
Jul 1, 2007(actual)

Against the original forecast

  • Construction start8 months lateforecast Jul 31, 2006
  • Construction end7 months lateforecast Nov 30, 2006