R.M. of Whitehead - Lagoon Liner
Federal contribution
$166,667
Federal share27%
of $625.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2006
2007
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Whitehead
- Construction start
- Dec 19, 2006(actual)
- Construction end
- Oct 4, 2007(actual)
Against the original forecast
- Construction start6 months lateforecast Jun 15, 2006
- Construction end20 months earlyforecast Jun 15, 2009
Also in Alexander