Alexander Ward 4 Wastewater Lagoon System
Federal contribution
$569,600
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2022
2023
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Alexander
- Construction start
- Aug 2, 2022(actual)
- Construction end
- Oct 10, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2022
- Construction end3 months earlyforecast Dec 31, 2023
Also in Alexander