St. Peter's/Sampsonville Water System Upgrade - Phase I
Federal contribution
$1.6M
$1,569,532
Federal share33%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2007
2007200820092010
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of St. Peter's
- Construction start
- Jul 27, 2006(actual)
- Construction end
- Mar 26, 2010(actual)
Against the original forecast
- Construction start8 months lateforecast Nov 24, 2005
Also in Sampsonville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15856 in the federal list. How to read these figures.