Schedule

Announced and approvedMar 9, 2007
2007200820092010
Built

Approved 7 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of St. Peter's
Construction start
Jul 27, 2006(actual)
Construction end
Jun 1, 2010(actual)

Against the original forecast

  • Construction start8 months lateforecast Nov 24, 2005
  • Construction end2 months lateforecast Mar 31, 2010

Also in Sampsonville