St. Peter's/Sampsonville Water System Upgrade - Phase II
Federal contribution
$656,208
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2007
2007200820092010
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of St. Peter's
- Construction start
- Jul 27, 2006(actual)
- Construction end
- Jun 1, 2010(actual)
Against the original forecast
- Construction start8 months lateforecast Nov 24, 2005
- Construction end2 months lateforecast Mar 31, 2010
Also in Sampsonville