Back to projects

Wetlands - Kennedale & Pylypow

Edmonton, Alberta

completeWastewaterMRIF
Federal contribution
$3.0M
$3,000,000
Federal share29%

of $10.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
2007200820092010
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Edmonton
Construction start
Mar 27, 2007(actual)
Construction end
Sep 10, 2010(actual)

Also in Edmonton