Three New Transit Centres
Federal contribution
$4.6M
$4,600,000
Federal share19%
of $24.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2007
20072008200920102011
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Edmonton
- Construction start
- Jun 30, 2008(actual)
- Construction end
- Sep 19, 2011(actual)
Also in Edmonton