Back to projects

New Middle School access and Servicing

Millet, Alberta

completeHighways and RoadsMRIF
Federal contribution
$710,800
Federal share32%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 23, 2007
20072008200920102011
Built

Approved 4 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Millet
Construction start
Mar 1, 2009(actual)
Construction end
Nov 16, 2010(actual)

Against the original forecast

  • Construction start22 months lateforecast May 1, 2007
  • Construction end8 months lateforecast Mar 31, 2010

Also in Millet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16120 in the federal list. How to read these figures.