New Middle School access and Servicing
Federal contribution
$710,800
Federal share32%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 23, 2007
20072008200920102011
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Millet
- Construction start
- Mar 1, 2009(actual)
- Construction end
- Nov 16, 2010(actual)
Against the original forecast
- Construction start22 months lateforecast May 1, 2007
- Construction end8 months lateforecast Mar 31, 2010
Also in Millet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16120 in the federal list. How to read these figures.