Back to projects

Millet Agriplex Upgrade

Millet, Alberta

completeRecreationRNIS
Federal contribution
$292,000
Federal share40%

of $730.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 25, 2020
2021
Built

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Millet
Construction start
Mar 22, 2021(actual)
Construction end
Oct 8, 2021(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Apr 15, 2021
  • Construction end6 weeks lateforecast Aug 30, 2021

Also in Millet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56653 in the federal list. How to read these figures.