Swimming Pool Retrofit
Federal contribution
$41,666
Federal share14%
of $304.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 13, 2007
2007200820092010
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Thorhild
- Construction start
- May 4, 2007(actual)
- Construction end
- Sep 2, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Mar 30, 2007
- Construction end20 months lateforecast Dec 31, 2008
Also in Thorhild