Swimming Pool Retrofit

Thorhild, Alberta

completeSportMRIF
Federal contribution
$41,666
Federal share14%

of $304.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2007
2007200820092010
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Thorhild
Construction start
May 4, 2007(actual)
Construction end
Sep 2, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Mar 30, 2007
  • Construction end20 months lateforecast Dec 31, 2008

Also in Thorhild

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16154 in the federal list. How to read these figures.