Long Lake Emergency Access Road
Federal contribution
$199,004
Federal share19%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 30, 2009
200920102011201220132014
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Thorhild No. 7
- Construction start
- Oct 10, 2012(actual)
- Construction end
- Dec 31, 2013(actual)
Against the original forecast
- Construction start3.5 years lateforecast Apr 1, 2009
- Construction end3.3 years lateforecast Sep 1, 2010
Also in Thorhild
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24898 in the federal list. How to read these figures.