Municipal Capacity Development Program (MCDP)

Regina, Saskatchewan

completeCapacity BuildingMRIF
Federal contribution
$390,744
Federal share50%

of $781.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 21, 2006
200720082009
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Sarm/Suma/Sanc
Construction start
Sep 14, 2006(actual)
Construction end
Aug 31, 2009(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2006
  • Construction end7 months earlyforecast Mar 31, 2010

Also in Regina

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16180 in the federal list. How to read these figures.