completeSolid Waste ManagementMRIF
Federal contribution
$2.6M
$2,600,000
Federal share33%

of $7.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 9, 2007
20072008200920102011
Built

Approved 2 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Drumheller
Construction start
Feb 23, 2007(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Apr 1, 2007
  • Construction end9 months lateforecast Mar 31, 2010

Also in Drumheller