Paving of Highway 9, East of Highway 836 to East of Highway 840
Federal contribution
$1.5M
$1,505,711
Federal share50%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 2, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Oct 10, 2009(actual)
- Construction end
- Aug 4, 2011(actual)
Against the original forecast
- Construction start7 months earlyforecast May 15, 2010
- Construction end2 months earlyforecast Oct 15, 2011
Also in Drumheller
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28476 in the federal list. How to read these figures.