Treated Water Expansion
Federal contribution
$55,025
Federal share25%
of $220.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 28, 2007
20082009
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of St. Brieux
- Construction start
- Jul 24, 2007(actual)
- Construction end
- Dec 17, 2008(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2007
- Construction end3 months earlyforecast Mar 31, 2009
Also in St. Brieux
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16358 in the federal list. How to read these figures.