Back to projects

Town of St Brieux Lagoon Wastewater Upgrade

St. Brieux, Saskatchewan

underwayWastewaterGIS
Federal contribution
$1.3M
$1,304,200
Federal share40%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
202120222023202420252026
BuiltForecast

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of St. Brieux
Construction start
Sep 6, 2024(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start5 months lateforecast Apr 22, 2024

Also in St. Brieux

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57219 in the federal list. How to read these figures.