Road Reconstruction
Federal contribution
$200,237
Federal share9%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2007
200720082009
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Old Post
- Construction start
- Jan 3, 2007(actual)
- Construction end
- Dec 31, 2008(actual)
Against the original forecast
- Construction end3 months earlyforecast Mar 31, 2009
Also in Wood Mountain
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16368 in the federal list. How to read these figures.