Road Reconstruction

Wood Mountain, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$200,237
Federal share9%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
200720082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 3, 2007(actual)
Construction end
Dec 31, 2008(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2009