Wood Mountain Regional Park Pool Upgrade
Federal contribution
$104,205
Federal share25%
of $416.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2008
20082009
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Old Post
- Construction start
- Dec 14, 2007(actual)
- Construction end
- Oct 27, 2009(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2010
Also in Wood Mountain
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18845 in the federal list. How to read these figures.