Road Reconstruction

Burstall, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$41,790
Federal share25%

of $167.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 3, 2007
2008
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 24, 2007(actual)
Construction end
Jul 9, 2008(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007
  • Construction end9 months earlyforecast Mar 31, 2009