New Water Treatment Plant

Burstall, Saskatchewan

completeDrinking WaterCC
Federal contribution
$471,759
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 20, 2009
2009201020112012
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Burstall
Construction start
Oct 5, 2009(actual)
Construction end
Jun 5, 2012(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2009
  • Construction end10 months earlyforecast Mar 31, 2013