Construction of the Northern Bruce Peninsula Waste Diversion Facility

Northern Bruce Peninsula, Ontario

completeSolid Waste ManagementMRIF
Federal contribution
$250,166
Federal share33%

of $750.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
2007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 1, 2007(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction end3 months lateforecast Sep 30, 2009