Municipal Building for Tourism and Public Washroom Facility
Northern Bruce Peninsula, Ontario
Federal contribution
$133,333
Federal share33%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Northern Bruce Peninsula
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 30, 2010
Also in Northern Bruce Peninsula
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29984 in the federal list. How to read these figures.