Rehabilitation of Healey Falls Bridge

Campbellford, Ontario

completeHighways and RoadsMRIF
Federal contribution
$472,667
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Northumberland
Construction start
Dec 22, 2006(actual)
Construction end
Jul 17, 2009(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end10 months lateforecast Sep 30, 2008