Municipality of Trent Hills Asset Management
Federal contribution
$5,239
Federal share33%
of $15.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008200920102011
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Trent Hills
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Mar 21, 2011(actual)
Also in Campbellford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18209 in the federal list. How to read these figures.