Langenburg Reverse Osmosis
Federal contribution
$171,031
Federal share25%
of $684.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
200720082009
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Langenburg
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Dec 2, 2008(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2007
- Construction end4 months earlyforecast Mar 31, 2009
Also in Langenburg