Langenburg Reverse Osmosis

Langenburg, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$171,031
Federal share25%

of $684.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
200720082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Langenburg
Construction start
Dec 20, 2006(actual)
Construction end
Dec 2, 2008(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end4 months earlyforecast Mar 31, 2009

Also in Langenburg