Community Centre Roof
Federal contribution
$35,832
Federal share25%
of $143.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 22, 2008
20082009
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Langenburg
- Construction start
- Dec 14, 2007(actual)
- Construction end
- Mar 26, 2009(actual)
Also in Langenburg