Replacement of the Mitchell Creek Bridge
Federal contribution
$170,818
Federal share33%
of $512.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
200720082009
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of South Frontenac
- Construction start
- Apr 1, 2007(actual)
- Construction end
- Dec 16, 2008(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Dec 31, 2008
Also in South Frontenac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16484 in the federal list. How to read these figures.