Battersea Road
Federal contribution
$325,000
Federal share33%
of $975.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of South Frontenac
- Construction start
- Nov 23, 2009(actual)
- Construction end
- Aug 13, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 4, 2009
- Construction end7 weeks earlyforecast Sep 30, 2010
Also in South Frontenac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31243 in the federal list. How to read these figures.