Battersea Road

South Frontenac, Ontario

completeHighways and RoadsISF
Federal contribution
$325,000
Federal share33%

of $975.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of South Frontenac
Construction start
Nov 23, 2009(actual)
Construction end
Aug 13, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Nov 4, 2009
  • Construction end7 weeks earlyforecast Sep 30, 2010

Also in South Frontenac