Reconstruction of the Mary Street Bridge
Federal contribution
$752,213
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
2007
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Pembroke
- Construction start
- Jan 15, 2007(actual)
- Construction end
- Nov 30, 2007(actual)
Against the original forecast
- Construction end16 months earlyforecast Mar 31, 2009
Also in Pembroke
- HVAC System UV Treatment; HVAC Duct Sealing; Ventilation$2.2M
- Reconstruction of a Section of Pembroke Street West$2.0M
- Bennet Street and Boundary Road Watermain Replacement and Taylor Bridge Watermain Suspension$1.9M
- HVAC Upgrades; Portable Replacement; Installation of Bottle Filling Stations$1.5M
- Algonquin Trail North Active Transportation Enhancements$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16503 in the federal list. How to read these figures.