Clay Capping
Federal contribution
$35,683
Federal share25%
of $142.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 3, 2007
2008
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Reford
- Construction start
- Jul 24, 2007(actual)
- Construction end
- Nov 10, 2008(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2007
- Construction end7 months lateforecast Mar 31, 2008
Also in Nokomis
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16544 in the federal list. How to read these figures.