Town of Nokomis Lagoon Expansion

Nokomis, Saskatchewan

completeWastewaterGIS
Federal contribution
$543,775
Federal share40%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
202120222023202420252026
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Nokomis
Construction start
Jun 2, 2025(actual)
Construction end
Nov 21, 2025(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2025

Also in Nokomis

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57139 in the federal list. How to read these figures.