Treated Water Storage Reservoir
Federal contribution
$178,750
Federal share25%
of $715.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2007
20072008
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Warman
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Mar 10, 2008(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2007
- Construction end3 weeks earlyforecast Mar 31, 2008
Also in Warman
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16622 in the federal list. How to read these figures.