City of Warman Sewage Treatment Lagoon Expansion and Improvements

Warman, Saskatchewan

completeWastewaterGIS
Federal contribution
$7.2M
$7,240,000
Federal share40%

of $18.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2019
2020202120222023
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Warman
Construction start
Jul 1, 2020(actual)
Construction end
Aug 1, 2023(actual)

Against the original forecast

  • Construction start5 months earlyforecast Nov 30, 2020
  • Construction end2 months lateforecast Jun 1, 2023