City of Warman Sewage Treatment Lagoon Expansion and Improvements
Federal contribution
$7.2M
$7,240,000
Federal share40%
of $18.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2019
2020202120222023
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Warman
- Construction start
- Jul 1, 2020(actual)
- Construction end
- Aug 1, 2023(actual)
Against the original forecast
- Construction start5 months earlyforecast Nov 30, 2020
- Construction end2 months lateforecast Jun 1, 2023