Water Distribution System Waterflow and Fireflow Upgrade
Federal contribution
$339,962
Federal share33%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
20072008
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Truro
- Construction start
- Jan 22, 2007(actual)
- Construction end
- Dec 2, 2008(actual)
Against the original forecast
- Construction start14 months lateforecast Nov 24, 2005
- Construction end4 months earlyforecast Mar 31, 2009
Also in Truro
- NSNWA Resilience Center$6.6M
- Upgrade of the Colchester County Wastewater Treatment Facility$3.5M
- Truro Amateur Athletic Club Multi-use Sport Facility Revitalization and Relocation of Senior Baseball Facility$3.2M
- Bio-Solids Handling Facility$1.5M
- Town of Truro - McClures Mills Road & Willow Street Roundabout$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16672 in the federal list. How to read these figures.