Heavy Haul Road Restoration

Maidstone, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$250,000
Federal share14%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 3, 2007
20072008
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Rural Municipality of Eldon
Construction start
Dec 20, 2006(actual)
Construction end
Dec 19, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end3 months earlyforecast Mar 31, 2008

Also in Maidstone