Town of Maidstone Water Supply Expansion

Maidstone, Saskatchewan

underwayDrinking WaterGIS
Federal contribution
$187,742
Federal share40%

of $469.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
today
2024202520262027
BuiltForecast

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Maidstone
Construction start
Dec 4, 2023(actual)
Construction end
Mar 31, 2027(forecast)

Against the original forecast

  • Construction start4 months earlyforecast Apr 1, 2024

Also in Maidstone

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67485 in the federal list. How to read these figures.