Waterworks Upgrade
Federal contribution
$159,162
Federal share25%
of $636.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2007
20082009201020112012
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Montmartre
- Construction start
- Jul 24, 2007(actual)
- Construction end
- Mar 30, 2012(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2007
Also in Montmartre
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16845 in the federal list. How to read these figures.