Sewage Lagoon Expansion
Federal contribution
$310,152
Federal share27%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
2019202020212022
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Montmartre
- Construction start
- Jun 15, 2020(actual)
- Construction end
- Dec 8, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2020
- Construction end4 months earlyforecast Mar 31, 2022
Also in Montmartre
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52585 in the federal list. How to read these figures.