Main Sewage Lift Station Replacement

Maple Creek, Saskatchewan

completeWastewaterMRIF
Federal contribution
$239,725
Federal share25%

of $958.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 3, 2007
2008
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Maple Creek
Construction start
Jul 10, 2007(actual)
Construction end
Apr 14, 2008(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2007
  • Construction end2 weeks lateforecast Mar 31, 2008