Back to projects

Town of Maple Creek Wastewater Treatment Upgrades

Maple Creek, Saskatchewan

completeWastewaterNRP
Federal contribution
$2.0M
$1,980,000
Federal share33%

of $5.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2019
20192020202120222023
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Town of Maple Creek
Construction start
May 27, 2020(actual)
Construction end
Feb 9, 2023(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 30, 2019
  • Construction end7 months earlyforecast Aug 31, 2023

Also in Maple Creek

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52962 in the federal list. How to read these figures.