Fluoride

Frontier, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$101,138
Federal share25%

of $404.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 3, 2007
20082009201020112012
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Frontier
Construction start
Jul 24, 2007(actual)
Construction end
Apr 3, 2012(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007