Village of Frontier - Frontier Landfill Decommissioning

Frontier, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$109,039
Federal share40%

of $272.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2021
20212022202320242025
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Frontier
Construction start
Aug 17, 2021(actual)
Construction end
Dec 18, 2024(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2025

Also in Frontier

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57442 in the federal list. How to read these figures.