Water Treatment Expansion & Renovation
Federal contribution
$250,000
Federal share20%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
200720082009
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Churchbridge
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Dec 11, 2008(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 1, 2007
- Construction end4 months earlyforecast Mar 31, 2009
Also in Churchbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17001 in the federal list. How to read these figures.