Water Treatment System Upgrades

Churchbridge, Saskatchewan

completeDrinking WaterSCF
Federal contribution
$748,333
Federal share33%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
2019202020212022
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Churchbridge
Construction start
Sep 29, 2020(actual)
Construction end
Mar 15, 2022(actual)

Against the original forecast

  • Construction start14 months lateforecast Aug 1, 2019
  • Construction end9 months earlyforecast Nov 30, 2022