Water Treatment System Upgrades
Federal contribution
$748,333
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
2019202020212022
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Churchbridge
- Construction start
- Sep 29, 2020(actual)
- Construction end
- Mar 15, 2022(actual)
Against the original forecast
- Construction start14 months lateforecast Aug 1, 2019
- Construction end9 months earlyforecast Nov 30, 2022
Also in Churchbridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52580 in the federal list. How to read these figures.