Chase Wastewater Lift Station
Federal contribution
$244,666
Federal share33%
of $734.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 26, 2007
200820092010
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Chase
- Construction start
- Sep 4, 2007(actual)
- Construction end
- Mar 31, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 21, 2007