Village of Chase Community Building Improvements
Federal contribution
$197,529
Federal share80%
of $246.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Chase
- Construction start
- Nov 18, 2022(actual)
- Construction end
- Jun 16, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast Nov 30, 2021
- Construction end2 weeks lateforecast May 31, 2023