Village of Chase Community Building Improvements

Chase, British Columbia

completeVentilationCVRIS
Federal contribution
$197,529
Federal share80%

of $246.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Chase
Construction start
Nov 18, 2022(actual)
Construction end
Jun 16, 2023(actual)

Against the original forecast

  • Construction start12 months lateforecast Nov 30, 2021
  • Construction end2 weeks lateforecast May 31, 2023

Also in Chase

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60389 in the federal list. How to read these figures.