Calgary Downtown District Energy

Calgary, Alberta

completeGreen EnergyMRIF
Federal contribution
$10.0M
$10,000,000
Federal share25%

of $40.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2007
200820092010
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Calgary
Construction start
Apr 17, 2007(actual)
Construction end
Aug 4, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 1, 2007
  • Construction end4 months lateforecast Mar 31, 2010

Also in Calgary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17052 in the federal list. How to read these figures.